Berea Account#(New/Old): 7288
Transaction Date
|
Transaction Type
|
Contractor Name
|
Req Type
|
Comments
|
Check Number
|
Check Paid Date
|
Transaction Amount
|
|
03/31/2016 |
Encumbrance |
Technical Services |
|
Encumber Contractor |
|
|
$33,000.00 |
|
03/31/2016 |
Encumbrance |
OWDA Fee |
|
Encumber Contractor |
|
|
$5,929.00 |
|
03/31/2016 |
Encumbrance |
Contingencies |
|
Encumber Contractor |
|
|
$187,474.10 |
|
03/31/2016 |
Encumbrance |
Aclara Technologies |
|
Encumber Contractor |
|
|
$452,817.00 |
|
03/31/2016 |
Encumbrance |
Badger Meter, Inc. |
|
Encumber Contractor |
|
|
$411,357.00 |
|
03/31/2016 |
Encumbrance |
Neptune Equipment Company |
|
Encumber Contractor |
|
|
$609,422.90 |
|
04/01/2016 |
Loan Fee Billed |
N/A |
|
Loan Fee Billed |
|
|
$5,929.00 |
|
05/18/2016 |
Disbursement |
OWDA Fee |
Loan Fee: |
|
1390459 |
05/19/2016 |
$5,929.00 |
|
05/25/2016 |
Loan Fee Paid |
N/A |
|
Loan Fee Payment |
|
05/25/2016 |
($5,929.00) |
|
05/26/2016 |
Contingency Set-asid |
Neptune Equipment Company |
|
embedded contingency |
|
|
$100,000.00 |
|
05/31/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$4.80 |
|
06/29/2016 |
Change Order |
Contingencies |
|
No. 1 for Badger Meter, Inc. in the amount of $320.00 |
|
|
($320.00) |
|
06/29/2016 |
Change Order |
Badger Meter, Inc. |
|
No. 1 for Badger Meter, Inc. in the amount of $320.00 |
|
|
$320.00 |
|
06/30/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$12.00 |
|
07/06/2016 |
Disbursement |
Badger Meter, Inc. |
Estimate: 1 |
|
Wire |
07/07/2016 |
$239,805.00 |
|
07/31/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$400.24 |
|
08/03/2016 |
Disbursement |
Neptune Equipment Company |
Estimate: 1 |
|
Wire |
08/04/2016 |
$66,391.20 |
|
08/10/2016 |
Disbursement |
Aclara Technologies |
Estimate: 1 |
|
Wire |
08/11/2016 |
$123,760.00 |
|
08/10/2016 |
Disbursement |
Aclara Technologies |
Estimate: 2 |
|
Wire |
08/11/2016 |
$3,250.00 |
|
08/10/2016 |
Disbursement |
Aclara Technologies |
Estimate: 3 |
|
Wire |
08/11/2016 |
$266,040.00 |
|
08/10/2016 |
Disbursement |
Badger Meter, Inc. |
Estimate: 2 |
|
Wire |
08/11/2016 |
$15,253.00 |
|
08/24/2016 |
Transfer |
Contingencies |
|
Per LGA letter dated 8/24/2016 |
|
|
($10,980.00) |
|
08/24/2016 |
Transfer |
Aclara Technologies |
|
Per LGA letter dated 8/24/2016 |
|
|
$10,980.00 |
|
08/31/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$1,184.45 |
|
09/01/2016 |
Transfer |
Technical Services |
|
Per LGA letter dated 8/30/2016 |
|
|
$23,000.00 |
|
09/01/2016 |
Transfer |
Contingencies |
|
Per LGA letter dated 8/30/2016 |
|
|
($23,000.00) |
|
09/21/2016 |
Disbursement |
Technical Services |
Prof Services: FPR 7 |
|
Wire |
09/22/2016 |
$38,255.87 |
|
09/21/2016 |
Disbursement |
Badger Meter, Inc. |
Estimate: 3 |
|
Wire |
09/22/2016 |
$84,046.00 |
|
09/21/2016 |
Disbursement |
Neptune Equipment Company |
Estimate: 2 |
|
Wire |
09/22/2016 |
$76,382.32 |
|
09/28/2016 |
Disbursement |
Aclara Technologies |
Estimate: 4 |
|
Wire |
09/29/2016 |
$35,112.05 |
|
09/29/2016 |
Change Order |
Contingencies |
|
No. 2 for Badger Meter in the amount of $28,168.00 |
|
|
($28,168.00) |
|
09/29/2016 |
Change Order |
Badger Meter, Inc. |
|
No. 2 for Badger Meter in the amount of $28,168.00 |
|
|
$28,168.00 |
|
09/30/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$1,565.99 |
|
10/05/2016 |
Contingency Set-asid |
Neptune Equipment Company |
|
No. 3 for Neptune Equipment in the amount of $1,188.91 |
|
|
($1,188.91) |
|
10/05/2016 |
Disbursement |
Technical Services |
Prof Services: FPR 11 |
|
Wire |
10/06/2016 |
$2,598.00 |
|
10/11/2016 |
Transfer |
Technical Services |
|
Per LGA email dated 10/11/2016 |
|
|
$5,876.00 |
|
10/11/2016 |
Transfer |
Contingencies |
|
Per LGA email dated 10/11/2016 |
|
|
($5,876.00) |
|
10/19/2016 |
Disbursement |
Badger Meter, Inc. |
Estimate: 4 |
|
Wire |
10/20/2016 |
$76,030.00 |
|
10/19/2016 |
Disbursement |
Neptune Equipment Company |
Estimate: 3 |
|
Wire |
10/20/2016 |
$97,000.80 |
|
10/31/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$2,126.37 |
|
11/09/2016 |
Disbursement |
Technical Services |
Prof Services: FPR 15 |
|
Wire |
11/10/2016 |
$2,489.76 |
|
11/09/2016 |
Disbursement |
Technical Services |
Reimbursement: FPR 14 |
|
Wire |
11/10/2016 |
$5,876.00 |
|
11/30/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$2,295.90 |
|
11/30/2016 |
Disbursement |
Technical Services |
Prof Services: FPR 16 |
|
Wire |
12/01/2016 |
$2,451.80 |
|
12/21/2016 |
Disbursement |
Technical Services |
Prof Services: FPR 19 |
|
Wire |
12/22/2016 |
$1,357.63 |
|
12/21/2016 |
Disbursement |
Aclara Technologies |
Estimate: 5 |
|
Wire |
12/22/2016 |
$5,161.65 |
|
12/21/2016 |
Disbursement |
Neptune Equipment Company |
Estimate: 4 |
|
Wire |
12/22/2016 |
$124,279.37 |
|
12/28/2016 |
Disbursement |
Aclara Technologies |
Estimate: 6 |
|
Wire |
12/29/2016 |
$27,973.30 |
|
12/31/2016 |
Capitalized Interest |
N/A |
|
Period Capitalized Interest |
|
|
$2,466.58 |
|
01/18/2017 |
Disbursement |
Technical Services |
Prof Services: FPR 21 |
|
Wire |
01/19/2017 |
$378.86 |
|
02/17/2017 |
Contingency Set-asid |
Neptune Equipment Company |
|
No. 4 for Neptune Equipment Company in the amount of $3,714.00 |
|
|
($3,714.00) |
|
03/01/2017 |
Disbursement |
Neptune Equipment Company |
Estimate: 5 |
|
Wire |
03/02/2017 |
$67,386.07 |
|
03/21/2017 |
Change Order |
Contingencies |
|
No. 3 for Badger Meter, Inc. in the amount of $3,065.00 |
|
|
($3,065.00) |
|
03/21/2017 |
Change Order |
Badger Meter, Inc. |
|
No. 3 for Badger Meter, Inc. in the amount of $3,065.00 |
|
|
$3,065.00 |
|
03/29/2017 |
Disbursement |
Technical Services |
Prof Services: FPR 23 |
|
Wire |
03/30/2017 |
$1,041.90 |
|
05/31/2017 |
Disbursement |
Technical Services |
Prof Services: FPR 24 |
|
Wire |
06/01/2017 |
$1,222.48 |
|
07/05/2017 |
Disbursement |
Neptune Equipment Company |
Estimate: 6 |
|
Wire |
07/06/2017 |
$6,576.85 |
|
07/05/2017 |
Interest Payment |
N/A |
|
|
|
07/03/2017 |
($21,033.69) |
|
07/05/2017 |
Principal Payment |
N/A |
|
|
|
07/03/2017 |
($33,350.67) |
|
08/02/2017 |
Disbursement |
Technical Services |
Prof Services: FPR 26 |
|
Wire |
08/03/2017 |
$221.75 |
|
09/20/2017 |
Encumbrance |
Technical Services |
|
Un-Encumber Contractor - Loan Closed |
|
|
($5,981.95) |
|
09/20/2017 |
Encumbrance |
Contingencies |
|
Un-Encumber Contractor - Loan Closed |
|
|
($116,065.10) |
|
09/20/2017 |
Encumbrance |
Aclara Technologies |
|
Un-Encumber Contractor - Loan Closed |
|
|
($2,500.00) |
|
09/20/2017 |
Encumbrance |
Badger Meter, Inc. |
|
Un-Encumber Contractor - Loan Closed |
|
|
($27,776.00) |
|
09/20/2017 |
Encumbrance |
Neptune Equipment Company |
|
Un-Encumber Contractor - Loan Closed |
|
|
($171,406.29) |
|
09/30/2017 |
Interest Adj Cost Ch |
N/A |
|
|
|
|
$3,981.73 |
|
09/30/2017 |
Principal Adj Cost C |
N/A |
|
|
|
|
($3,981.73) |
|
01/03/2018 |
Interest Payment |
N/A |
|
|
|
01/02/2018 |
($16,719.14) |
|
01/03/2018 |
Principal Payment |
N/A |
|
|
|
01/02/2018 |
($17,074.32) |
|
07/03/2018 |
Interest Payment |
N/A |
|
|
|
07/02/2018 |
($16,382.62) |
|
07/03/2018 |
Principal Payment |
N/A |
|
|
|
07/02/2018 |
($27,706.29) |
|
01/03/2019 |
Interest Payment |
N/A |
|
|
|
01/02/2019 |
($16,041.83) |
|
01/03/2019 |
Principal Payment |
N/A |
|
|
|
01/02/2019 |
($28,047.08) |
|
07/02/2019 |
Interest Payment |
N/A |
|
|
|
07/01/2019 |
($15,696.86) |
|
07/02/2019 |
Principal Payment |
N/A |
|
|
|
07/01/2019 |
($28,392.05) |
|
01/06/2020 |
Interest Payment |
N/A |
|
|
|
01/03/2020 |
($15,347.63) |
|
01/06/2020 |
Principal Payment |
N/A |
|
|
|
01/03/2020 |
($28,741.28) |
|
07/01/2020 |
Interest Payment |
N/A |
|
|
|
07/01/2020 |
($14,994.11) |
|
07/01/2020 |
Principal Payment |
N/A |
|
|
|
07/01/2020 |
($29,094.80) |
|
01/04/2021 |
Interest Payment |
N/A |
|
|
|
01/04/2021 |
($14,636.24) |
|
01/04/2021 |
Principal Payment |
N/A |
|
|
|
01/04/2021 |
($29,452.67) |
|
07/02/2021 |
Interest Payment |
N/A |
|
|
|
07/01/2021 |
($14,273.98) |
|
07/02/2021 |
Principal Payment |
N/A |
|
|
|
07/01/2021 |
($29,814.93) |
|