Transaction Detail for Contractor CO - Contingencies
Transaction
Date
Transaction
Type
Req
Type
Comments Check
Number
Check
Paid
Date
Disbursement
Transaction
Amount
Encumbrance
Transaction
Amount
Balance
01/31/2019 Encumbrance         $0.00 $5,694,454.00 $5,694,454.00
04/27/2019 Transfer   Transferring embedded contingency to contractor's line item     $0.00 ($260,000.00) $5,434,454.00
02/04/2020 Change Order   No. 1 for The Great Lakes Construction Co. in the amount of $167,055.58     $0.00 ($167,055.58) $5,267,398.42
10/05/2020 Transfer   Per DEFA transfer email 10.5.20, add. design services     $0.00 ($180,000.00) $5,087,398.42
12/18/2020 Change Order   No. 3 for The Great Lakes Construction Co. $1,172,547.76     $0.00 ($1,172,547.76) $3,914,850.66
            Total: $0.00 $3,914,850.66  